Power Maintenance
Scheduled Maintenance Report for Simply Hosting & Servers
Completed
This maintenance period is now being marked as complete, there will be no further works today on the STS.
Posted Jun 21, 2017 - 14:39 BST
Verifying
The maintenance has been completed and we have moved off of the maintenance bypass.

We will monitor the situation for another hour before marking as complete.
Posted Jun 21, 2017 - 12:51 BST
Update
We can now confirm that the maintenance has started and the STS is in maintenance bypass mode.
Posted Jun 21, 2017 - 12:28 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 21, 2017 - 09:00 BST
Scheduled
On 21st June from 09:00 to 17:00 BST engineers are performing maintenance to an STS power switch system that supplies a proportion of our Reading data centre.

During the window it will be put into maintenance bypass. Services will still be protected by the A side UPS system but unable to transfer to the B side UPS system.

No interruption is anticipated but it is an ‘at risk’ period with reduced level of redundancy.
Posted Jun 07, 2017 - 10:03 BST